Key takeaways
- Build the equipment list from the approved TGS, approach by approach, not from memory or last week's job.
- Count signs, stands, ballast, cones, covers, lights and barriers separately, then add sensible spares for damage and changes on site.
- Check the TGS revision and the sign sizes it calls for before packing; a superseded drawing is the most common cause of the wrong kit.
- Load the ute in reverse order of set-up, so the first sign you need is the easiest to reach.
- A printed or digital checklist ticked at the depot and again on site catches missing items before traffic does.
A good TGS equipment list comes straight from the approved traffic guidance scheme: go through each approach, count every sign and device it shows, then add stands, ballast, covers, lighting, pedestrian devices, communications and spares. Load the vehicle in reverse set-up order and tick the list off at the depot and again on site.
This article shows the method and walks through an example list for a typical job. The TGS itself must be prepared by a suitably qualified person, and nothing here replaces it or your state's requirements. This is general information, not legal or engineering advice. If reading the drawing is still new to you, start with how to read a traffic guidance scheme.
Why packing from the TGS matters
Most "wrong kit" problems are not about forgetting cones. They are about packing for the job in your head rather than the job on the drawing:
- The TGS is a revised version, and the extra sign added after the council's comments is not on the ute.
- The road is faster than the crew assumed, and the TGS calls for larger signs than the ones packed.
- The job is a night shift, and nobody packed lights for the signs or the controller stations.
- There is a footpath closure on the TGS that the crew did not see because they only looked at the traffic lanes.
- The permanent speed sign inside the works needs a cover, and there are no covers on the ute.
Each of these is found either at the depot, when it costs ten minutes, or on site, when it costs a delay, a site that does not match the plan, or a crew member driving back to the yard.
The method: approach by approach
Work through the TGS in a fixed order so nothing is missed. In this example method, the person packing:
- Checks the title block: project, location, TGS number, revision, date and approval. Confirm the revision matches the one in the job pack.
- Notes the speed, the shift type (day or night) and the duration, because these drive sign size, lighting and ballast.
- Takes the first approach and lists every sign from the furthest upstream to the end of the works, writing the sign code or description and the quantity.
- Repeats for each approach, including side streets and driveways shown on the drawing.
- Lists delineation: cones, bollards, barrier boards, and the number of each from the drawing's notes or the arithmetic below.
- Lists other devices: stop/slow bats, portable traffic signals, arrow boards, VMS, TMA, barriers.
- Lists pedestrian and cyclist devices: pedestrian barriers, ramps, detour signs.
- Lists covers for any permanent signs the TGS says to cover.
- Adds support items: stands, ballast, lights, radios, spare batteries.
- Adds spares to the company's standard.
- Adds documents: the TGS, the approval, the SWMS and any permit conditions.
Worked example: a stop/slow lane closure
Example scenario: the TGS is for a single-lane closure with stop/slow on a two-lane, two-way road, day shift. Below is how the list comes together. The quantities are what this example TGS shows, not standard requirements; your TGS will be different.
| Item | Approach A | Approach B | Work area | Spares | Total |
|---|---|---|---|---|---|
| Roadwork ahead sign | 1 | 1 | 2 | ||
| Prepare to stop sign | 1 | 1 | 2 | ||
| Traffic controller ahead sign | 1 | 1 | 2 | ||
| Temporary speed sign | 1 | 1 | 2 | ||
| End roadwork sign | 1 | 1 | 2 | ||
| Sign stands | 5 | 5 | 1 | 11 | |
| Sandbags or ballast | as per stand type | as per stand type | extra | per company standard | |
| Stop/slow bats | 1 | 1 | 2 | ||
| Cones | 23 | 5 | 28 | ||
| Covers for permanent speed sign | 2 | 1 | 3 | ||
| Radios | 3 | 1 battery each | 3 |
How the cone count works in this example: the example TGS shows the taper delineated with 8 cones and the work area with a further 15 at the spacing noted on the drawing, so 8 + 15 = 23. The company adds 5 spares for damaged or knocked devices. Spacings and taper lengths come from the TGS, which is based on AS 1742.3, the AGTTM and the state supplement for that speed and road. Our free cone calculator helps with the arithmetic once you know what the TGS specifies, and our guide to cone spacing and sizes explains the background.
What goes wrong in this example, and the fix: the allocator packed the ute from the original drawing. At the pre-start, the supervisor compares the revision on the job pack with the copy on the ute and finds the approved revision added a "lane closed" sign on approach B after a council comment. The supervisor gets one from the depot before set-up starts, and the job record notes the revision check. This is exactly why step 1 is the title block.
Second example: the same road at night with a footpath closure
Here is how the list changes on a typical job when the same stop/slow closure is booked as a night shift and the TGS adds a footpath closure on one side. The method is identical; the list is not.
- Lighting. The night procedure and TGS call for lighting at the controller stations and the work area, and illumination for the stop/slow arrangement. Lights, stands, fuel or charged batteries and spares go on the list.
- Retroreflective condition. Every sign and cone is checked for reflectivity, because at night it is the only thing drivers see. Faded signs that pass in daylight are swapped.
- Pedestrian devices. The footpath closure needs pedestrian barriers, signs at each end and at the nearest crossing point, and a ramp if the detour uses the road. These are counted from the drawing like any other device.
- Controller visibility. Night-rated PPE is checked at the pre-start, not assumed.
- Extra radio batteries. Cold nights and long shifts flatten them.
In this example the allocator uses the day-shift list as a starting point, then the supervisor checks it against the night TGS line by line. The second check finds that the pedestrian detour signs were not packed, because the day list had no footpath closure. Ten minutes at the depot fixes it.
Support items people forget
| Item | Why it gets forgotten | Check |
|---|---|---|
| Ballast for every stand | Counted once, not per stand | One set per stand, plus spare |
| Sign covers | Covers are for permanent signs, not on the TGS legend | Read the notes on the TGS |
| Night lighting | Day crew packed for a night job | Lights for signs, controller stations and work area as the TGS and night procedure require |
| Pedestrian barriers and ramps | Crew focused on traffic lanes | Check the footpath on the drawing |
| Spare radio batteries | Radios charged, spares not | One spare per radio |
| Bat wands or illumination | Night stop/slow needs more than the bat | Per the night procedure |
| Copies of the TGS and approval | Assumed to be "on the phone" | Printed or reliably accessible offline |
| End roadwork signs | Last sign on the drawing, first one missed | Count both approaches |
Sign stability matters on exposed sites and in wind. Ballast should be the type and quantity the stand manufacturer and the company procedure specify, and never rocks or loose items that could become projectiles. For signs themselves, our guide to common road work signs explains what each one is for.
Loading the ute in set-up order
Set-up starts with the furthest upstream advance sign and works towards the work area. So the ute should be loaded so the first signs you need are the easiest to reach, and the work-area devices come off last. A simple rule many crews use: "last needed, first loaded."
- Rear or most accessible position: advance signs for the first approach, with stands and ballast together.
- Next: signs for the second approach.
- Then: cones and delineation for the taper and work area.
- Separate, secure location: bats, radios, lights, documents.
- Restrained: everything. Loose signs and cones in a ute tray are a load restraint problem and a hazard on the road. Our guide to traffic control ute setup covers racking and restraint.
Pack-down is the reverse, and the list is useful again: tick each item as it comes back on board, so nothing is left on site.
Checking condition before it leaves the yard
Count is half the job. The other half is condition:
- Signs: faces clean, legible and retroreflective, with no fading, peeling or bent frames. A dull sign at night is not doing its job, however clean it looks in daylight.
- Stands: legs and locks working, the right stand for the sign size.
- Cones and bollards: reflective sleeves intact, bases not split.
- Lights and batteries: charged and tested.
- Bats: both faces clean, handle sound.
- TMA, arrow boards and VMS: inspection status current and the unit tested.
Damaged items are tagged out and not loaded. Recording defects in the equipment inspection log closes the loop; see equipment inspection logs.
The printable list: depot and site check
| Check | Depot | On site |
|---|---|---|
| TGS revision matches the approved version | ☐ | ☐ |
| Signs counted per approach, correct sizes | ☐ | ☐ |
| Stands and ballast, one per sign plus spares | ☐ | ☐ |
| Cones and delineation, plus spares | ☐ | ☐ |
| Covers for permanent signs | ☐ | ☐ |
| Pedestrian devices | ☐ | ☐ |
| Lighting (night shifts) | ☐ | ☐ |
| Bats, radios, spare batteries | ☐ | ☐ |
| TMA, arrow board, VMS checked | ☐ | ☐ |
| TGS, approval and SWMS on board | ☐ | ☐ |
| Load restrained | ☐ | n/a |
For the standards behind sign types and sizes, see Standards Australia for AS 1742.3 and Austroads for the AGTTM. NSW projects generally use Transport for NSW's TS 05492, which replaced the TCAWS manual on 25 June 2026; check the current version with Transport for NSW.
Next steps
Turn the method above into your company's standard packing sheet and use it on every job. If you run a traffic control company, TrafWise's equipment register tracks inspections, registration and insurance with renewal reminders, and printable QR labels let crew and office scan an item to see its record.
Frequently asked questions
How do you work out what equipment a TGS needs?
Go through the drawing one approach at a time, from the first advance sign to the end of the works, and list every sign, device and vehicle it shows. Then add stands, ballast, covers for permanent signs, lighting for night work, pedestrian devices, communications and spares. Check the revision number matches the approved plan.
How many spare cones and signs should a traffic control ute carry?
There is no single rule. Companies set their own allowance based on experience, the type of work and how far the site is from the depot. Common practice is to carry spare cones for knocked-over or damaged devices, spare sandbags and at least one spare of any sign that is easily damaged. Write your company's standard into the checklist.
Who is responsible for packing traffic control equipment?
It varies by company. Often the crew leader or supervisor is responsible for checking the equipment against the TGS before leaving the depot, with the allocator or yard staff preparing it in advance. Whoever packs it, the person who sets up the site must check it again on site before work starts.
What sign sizes does a TGS call for?
The TGS designer selects sign sizes based on the road's speed and conditions, using AS 1742.3, the AGTTM and the state's requirements. Larger signs are generally used on faster roads. Crews should pack the sizes shown on the TGS and not substitute smaller signs because they are easier to carry or all that is left in the yard.
What should you do if the site needs equipment not on the TGS?
Do not improvise a different layout. Call the supervisor, who decides whether the change is within what the TGS allows or needs the designer or approver. Record the change and the reason. Extra spares of the same devices are fine; adding new signs or devices changes the arrangement and needs approval.