Traffic cone calculator: how many cones does the job need?

Count the cones or delineators a layout needs before the ute is loaded. Enter the lengths and spacings from your TGS for each section, add spares and the number of stages, and get one number to load.

Start nowUse the tool free

No payment, no card. Just your name and email, once.

  • FreeNo card, no trial
  • WorldwideYour country's own rules
  • 7 featuresDevice count for the lead-in taper, buffer zone, work area and exit taper
  • Updated
06

Cone & delineator counter

Count the cones or bollards a layout needs before the ute is loaded, with spares. Enter the lengths and spacings shown on your traffic plan, or fill them from your country's rules and check each spacing against the maximum.

Rules
Sections
SectionLength mSpacing mLines
Lead-in taper
Buffer zone
Work area
Exit taper

Your numbers are saved on this device only. Nothing is sent anywhere.

How it's calculated

Each section needs (length ÷ spacing) + 1 devices per line, rounded up, because there is a device at both ends of a run. Sections that share an end point are counted once. Spares cover damaged, struck or blown-over devices and changes on the day. Lengths and spacings in the boxes are example values only: always use the figures on the traffic plan for the speed and layout you are setting out. "Fill from the rules" uses the taper length, buffer and maximum device spacing published for the country (and state) you picked, and marks any value the research couldn't confirm in the official text as “check”. Anything the rules don't give is left for you to enter.

FREE · NO CARD · NO CATCHBecome a free TrafWise member

One free account unlocks the full results, PDFs and downloads on every tool, and keeps you posted when a rule changes.

  • 1Your name and email
  • 2Enter the 6-digit code we email
  • 3Every tool opens, on every device

This traffic cone calculator counts the cones, bollards or delineators a layout needs, section by section, so the ute leaves the depot with enough. You enter the length and spacing the traffic guidance scheme (TGS) shows for the lead-in taper, buffer zone, work area and exit taper, add spares and stages, and get one number to load.

Running short of cones on site means either a gappy layout or someone driving back to the depot. Loading far too many wastes space you need for signs and gear. A two-minute count before you leave fixes both.

How it's worked out

Each section is counted the same way:

  • Devices per line = length ÷ spacing, rounded up.
  • Devices for the section = devices per line × number of lines.
  • The first section that has devices gets one extra device per line for its starting point. After that, each section's first device sits on the last device of the section before, so shared end points are only counted once.
  • Per site = all the sections added up.
  • Without spares = per site × the number of identical sites or stages.
  • To load = without spares × (1 + spare %), rounded up.

A section with zero lines, zero length or zero spacing is left out. Use 2 lines where cones run along both sides of a section, for example a buffer with a centreline and an edge line.

The default lengths and spacings in the boxes are examples only. Always use the figures on the TGS for the speed and layout you're setting out, and add devices for side roads, driveways and pedestrian routes.

The NSW spacing and taper rules

Under Transport for NSW's TS 05492 Traffic Control at Work Sites (June 2026), the maximum spacing depends on what the cones are for and the speed where they stand (Table 50):

PurposeSpeed zoneMaximum spacing
Approach to a traffic controller positionAll speeds4 m
Merge tapers60–70 km/h9 m
Merge tapers80 km/h and above12 m
Lateral shift tapers60–70 km/h12 m
Lateral shift tapers80 km/h and above18 m
All other purposesup to 50 km/h4 m
All other purposes60–70 km/h12 m
All other purposes80 km/h and above18 m

Spacing should be reduced on curves and crests, and where the cone row isn't clearly defined at night. Where volumes are high it can go down to 1 m.

Taper lengths come from Table 74. At 60 km/h a traffic control taper and a lateral shift taper are each 30 m and a merge taper is 60 m. A merge taper is 115 m at 70 km/h, 130 m at 80 km/h and 160 m at 100 km/h. Traffic control tapers aren't used from 70 km/h up. On multi-lane roads, Table 75 sets a minimum gap between tapers: 10 m up to 40 km/h, 25 m at 50, 70 m at 60 and 1.5 × the speed in metres from 70 km/h.

Cones also need to sit back from the traffic lane. Table 49 sets 0.5 m at 60 km/h or less and 1.0 m at 70 km/h and above, or 0.3 to 0.5 m behind the face of the kerb on kerbed roads. Our guide to traffic cone spacing and standards goes into each of these.

Traffic cone calculator worked example

A crew is closing the kerbside lane of a 60 km/h road for a 120 m work area. The TGS shows a 60 m merge taper, a 30 m buffer, the work area and a 20 m exit taper at 4 m spacing, with one line of cones throughout. They'll do it in two identical stages and want 10% spares.

SectionLengthSpacingCones
Merge taper60 m9 m60 ÷ 9 = 6.7, rounded up to 7, plus 1 at the start = 8
Buffer zone30 m12 m30 ÷ 12 = 2.5, rounded up to 3
Work area120 m12 m120 ÷ 12 = 10
Exit taper20 m4 m20 ÷ 4 = 5
Per site26
  • Two stages: 26 × 2 = 52.
  • Plus 10% spares: 52 × 1.1 = 57.2, rounded up to 58 cones to load.

If a traffic controller is also stopping traffic at one end, add the cones on the approach to their position at 4 m spacing. Twenty metres of approach adds 5 more per stage.

Queensland and other states

Queensland uses the Austroads Guide to Temporary Traffic Management (AGTTM) with its own differences in QGTTM Part 3. Two that change a cone layout:

  • The 200 m rule. Within the first 200 m after a speed drop, tapers use the higher speed. A taper that sits partly inside that 200 m uses the higher speed for its whole length.
  • Shuttle tapers. For shuttle flow, the traffic control taper must start at least 6 m from the traffic controller or portable device.

Queensland's cone spacing values aren't loaded into the calculator, so take them from the TGS. The same goes for Victoria, WA and SA, which build on AGTTM with their own codes of practice. The counting method works the same in every state: only the lengths and spacings change.

Tips for the load-out

  • Count from the TGS, not from memory. Spacing changes with speed, and a layout that worked last week at 50 km/h needs different spacing at 70 km/h.
  • Remember the extras. Side roads, driveways, pedestrian paths, plant access points and the approach to the controller all need devices the four sections don't cover.
  • Check the condition. Cones that are faded, cracked or missing their reflective sleeves don't count. Tag out damaged gear before loading. Our equipment inspection guide covers what to look for.
  • Load in set-up order. What goes out first should come off the ute first: advance signs, then the taper, buffer and work area.
  • Bring spares for nights. Spacing often needs to be reduced at night, so carry more than the daytime count.

The traffic control ute set-up guide shows a full load-out list.

When to get professional advice

The calculator counts what the TGS shows. It doesn't design the layout. Talk to the traffic management designer when:

  • the site doesn't fit the TGS lengths, for example because of a side road or driveway inside the taper
  • the speed on site differs from the speed on the TGS
  • the layout needs a change beyond the allowed tolerances

In NSW any moved sign must be marked and initialled on the site copy of the TGS, and bigger changes need the designer's approval. The set-up tolerance check helps you see whether a measured distance is still within tolerance, and the sign layout builder works out where the advance signs go.

Frequently asked questions

How many cones do I need for a lane closure?

Divide each section's length by the cone spacing, round up and add one at the start. A 60 m merge taper at 9 m spacing needs 8 cones, a 30 m buffer at 12 m needs 3 and a 120 m work area at 12 m needs 10. Add the exit taper and about 10% spares.

What is the maximum cone spacing in NSW?

TS 05492 Table 50 sets 4 m on the approach to a traffic controller at any speed. Merge tapers are 9 m at 60 to 70 km/h and 12 m at 80 km/h and above. For other purposes it's 4 m up to 50 km/h, 12 m at 60 to 70 km/h and 18 m at 80 km/h and above.

How long is a taper at 60 km/h?

In NSW, TS 05492 Table 74 recommends 30 m for a traffic control taper or lateral shift taper and 60 m for a merge taper at 60 km/h. At 100 km/h a merge taper is 160 m. Use the length on the approved TGS.

How far should cones be from the traffic lane?

TS 05492 Table 49 sets an edge clearance of 0.5 m for cones and bollards at 60 km/h or less and 1.0 m at 70 km/h and above. On kerbed roads devices go 0.3 to 0.5 m behind the face of the kerb.

How many spare cones should I carry?

There's no fixed rule. The calculator defaults to 10% extra, so 26 cones becomes 29, to replace struck or damaged cones and cover changes on the day. Add more for side roads, driveways and pedestrian routes the TGS shows.

Should cones be closer together at night?

TS 05492 says to reduce spacing on curves and crests, and where the cone row isn't clearly defined at night. Where volumes are high, spacing can go down to 1 m. The TGS spacing is the maximum, not a target.