Key takeaways
- Most traffic control subcontract disputes come from a handful of clauses: scope, minimums and standby, payment and set-off, indemnities, insurance and termination.
- Make the scope say who designs the TGS, who gets approvals, who supplies devices and who inspects the site overnight.
- Broad indemnities can make you liable for losses you did not cause, and your insurance may not cover them; ask your broker before you sign.
- WHS duties cannot be contracted away: the contract should support consultation, a right to stop unsafe work and fatigue limits.
- Get legal advice on any subcontract you will rely on; this guide helps you know which clauses to ask about.
The traffic control subcontract clauses that matter most are scope, rates and minimums, standby and cancellation, payment terms and set-off, indemnities and insurance, WHS responsibilities, and termination. Read those first, because they decide who pays when a job runs long, a TGS changes, a vehicle hits your signs or the client disputes an invoice. Get legal advice before relying on any of them.
A typical traffic control company signs dozens of subcontracts, purchase order terms and supplier agreements a year, usually under time pressure and often without reading past the rates. Most of the time nothing goes wrong. When something does, the clause you skipped decides the outcome. This guide is a practical reading list for operators, written from the operations side.
Know what you are actually signing
Before reading individual clauses, work out what kind of document it is and which terms win if they conflict.
- The principal's subcontract. Usually a standard form written for all trades and "back-to-back" with the head contract. Many clauses will not fit traffic control at all.
- Purchase order terms. The small print on the back of a PO can override what you thought you agreed by email.
- A master services agreement. Sets terms for ongoing call-off work, with each booking a separate order.
- Your own terms of trade. Useful for smaller clients, but large principals rarely accept them.
Look for the order of precedence clause. If it says the principal's general conditions override your quote, your carefully worded exclusions may disappear.
If you are a small business and the contract is offered on a take-it-or-leave-it basis, the national unfair contract terms laws may apply. Since 9 November 2023, unfair terms in standard form contracts with a small business, generally one with fewer than 100 employees or under $10 million turnover, are prohibited and penalties can apply. That is a reason to raise a clause, not a guarantee it is unenforceable.
Scope and responsibilities
Vague scope is the root of most disputes. A traffic control scope should say clearly:
- Who prepares the TGS and TMP, who pays for revisions and who is responsible if the design does not suit the site. A TGS must be prepared by a suitably qualified person.
- Who obtains approvals: road occupancy licences, council permits and police or transport authority notifications, and who pays the fees.
- Who supplies what: controllers, vehicles, signs, barriers, TMAs, VMS boards, lighting, pedestrian devices.
- Who inspects and maintains the site outside working hours, including after-care and overnight sign checks.
- Who directs your crew. Your supervisor should direct your workers; the principal's foreman should direct the work. Mixed lines of authority create safety problems.
- What happens when the TGS needs to change. Who can approve a change on site, and who pays for redesign and extra devices.
If the contract just says "provide traffic management as required", ask for a schedule that defines it.
Rates, minimums, standby and cancellations
These clauses decide whether a job makes money.
- Rates by time band: weekday day, night, Saturday, Sunday and public holiday rates, and the times each starts.
- Minimum charges: commonly 4 hours per controller and often 6 to 8 hours for vehicles and operators. If the subcontract is silent, the principal may argue they only pay actual hours. Our guide to minimum shift charges explains why they exist.
- Standby: a crew waiting because the client is not ready is still paid by you. The contract should say standby is chargeable.
- Cancellation: notice periods, and what is payable for cancellations inside them, including wet weather calls.
- Extensions and overtime: how time beyond the booking is charged and who on site can approve it.
- Rate review: award rates change through the Fair Work Commission's annual review. A fixed rate for a multi-year contract without a review mechanism is a slow loss.
Payment, set-off and security
Payment terms and claim dates
Note the claim date, the information each claim needs, the payment period and where invoices are lodged. Missing a monthly claim cut-off can cost a month of cash. Building a consistent evidence pack helps; see our guide to progress claim evidence.
Security of payment
Every state has construction security of payment legislation. Where it applies, it gives a statutory process to claim progress payments and have disputes decided by an adjudicator, and it limits how long payment can be delayed. In NSW, "pay when paid" provisions generally have no effect, and the Act is on the NSW legislation website. Whether your traffic control work is covered depends on the work and contract, and deadlines are strict, so get advice early.
Set-off and backcharges
Set-off clauses let the principal deduct amounts it says you owe: damage, delay costs, rectification or fines. Check what can be deducted, whether written notice is required and whether you can dispute it before money is withheld.
Retention and security
Some subcontracts ask for cash retention or a bank guarantee. For a labour-heavy service paid shift by shift, that can be hard to justify and painful to fund. Ask for it to be removed, capped or released promptly.
Time bars
Many contracts say a claim for a variation or extra cost is lost unless notified in writing within a set number of days. Crews and supervisors need to know these deadlines, or valid claims die in a site diary.
Indemnities, liability and insurance
Indemnities
An indemnity is a promise to cover another party's losses. A broad clause might require you to indemnify the principal for any loss "arising out of or in connection with" your work, even where the principal or a third party caused it. Common negotiated positions are to limit your indemnity to losses caused by your negligence or breach, and to reduce it to the extent the principal contributed.
Limitation of liability and consequential loss
Look for a cap on your total liability and an exclusion of consequential loss such as the principal's delay costs and lost profits. Without them, a single late start on a major project could expose you to costs far beyond the contract value.
Insurance
Contracts usually specify public liability cover, often naming the principal as an interested party, plus workers compensation, motor vehicle and sometimes professional indemnity if you design TGSs. The critical question is whether your policies actually respond to the liabilities the contract creates. Insurers commonly exclude liability you accept under a contract that you would not otherwise have. Send the risk clauses to your broker before signing. Our guide to traffic control insurance covers the main policies.
Damage to your equipment
Signs, boards and TMAs get hit by the public and sometimes by the principal's plant. Make sure the contract does not make you bear the loss when someone else causes it.
WHS and site control clauses
You cannot contract out of WHS duties. Where more than one business has duties for the same work, each must consult, cooperate and coordinate with the others. Safe Work Australia explains this shared-duty principle. Good subcontract clauses support it rather than shifting everything onto you.
Check for:
- Site rules and inductions you must follow, and who provides them.
- SWMS requirements. Work on or next to a road used by traffic is high-risk construction work, so a SWMS is needed before work starts; see our guide to traffic control SWMS.
- A right to stop work when traffic arrangements are unsafe or no longer match the TGS, without being in breach or losing payment for standby.
- Fatigue. Clauses requiring you to supply crews "as directed" for unlimited hours conflict with your fatigue management duties. Your fatigue limits should be respected in the contract.
- Incident notification timeframes and who notifies the regulator for notifiable incidents.
- Records: what you must provide, and the principal's right to audit them.
People, subcontracting and termination
- Qualifications and substitution: the contract may require named personnel or specific cards. Make sure you can substitute equally qualified workers.
- Subcontracting: many contracts require written consent before you send another company's crew. Our partner network is built for TC companies sharing work, but the contract with your client still decides whether you can.
- Non-solicitation: a clause stopping the principal from hiring your trained controllers directly may be worth asking for.
- Workers' status: if you engage individuals as contractors, the arrangement must be genuine. The Fair Work Ombudsman explains sham contracting risks.
- Termination for convenience: check notice periods and what you are paid for committed costs and demobilisation.
- Disputes: look for a practical escalation path before formal proceedings.
Traffic control subcontract clause checklist
| Clause | What you want | Red flag |
|---|---|---|
| Order of precedence | Your quote's inclusions and exclusions survive | General conditions override everything |
| Scope | TGS, approvals, devices and inspections allocated | "Traffic management as required" |
| Minimums and standby | Stated minimums, chargeable standby | Silence, or "actual hours only" |
| Cancellation | Clear notice period and charges | Cancellation anytime without cost |
| Payment | Defined claim dates and terms | Pay when paid; open-ended approval |
| Set-off | Notice and dispute before deduction | Unlimited unilateral deductions |
| Indemnity | Limited to your negligence or breach | Covers the principal's own negligence |
| Liability | Overall cap; consequential loss excluded | Unlimited liability |
| WHS | Right to stop unsafe work; fatigue limits respected | Crews supplied "as directed" without limits |
| Termination | Payment for committed costs | Termination at will without compensation |
Next steps
Use the checklist on your next subcontract and mark every clause that is missing or one-sided, then raise them before signing, not after the first dispute. Keep your rates, minimums and dockets aligned with what the contract says, and get legal advice on the clauses that carry real risk. TrafWise keeps signed dockets, approvals and shift records together, which is the evidence you will need if any of these clauses is ever tested.
Frequently asked questions
What should a traffic control subcontract include?
A clear scope covering TGS design, approvals, devices and inspections; rates for each time band; minimum charges, standby and cancellation terms; payment terms and claim dates; insurance requirements; indemnity and liability limits; WHS responsibilities; variation and dispute processes; and termination rights. Anything left vague becomes the subject of the first dispute.
Can a builder make me pay for their own negligence through an indemnity?
Some subcontract indemnities are drafted broadly enough to try. Whether they are enforceable and whether your insurance responds are questions for a lawyer and your broker. Ask for the indemnity to be reduced to the extent that your own negligence or breach caused the loss, which is a common negotiated position.
Do unfair contract terms laws protect small traffic control companies?
They can. Since 9 November 2023, unfair terms in standard form contracts with a small business, generally one with fewer than 100 employees or under $10 million turnover, are prohibited and penalties can apply. Whether a particular term is unfair depends on the circumstances, so seek legal advice.
Can a principal contractor withhold payment for backcharges?
Many subcontracts include set-off clauses that let the principal deduct amounts it says you owe. Check what can be set off, whether notice is required and how disputes are resolved. On construction work, security of payment laws may also give you rights to dispute the deduction through adjudication. Get legal advice quickly.
Can I subcontract traffic control work to another company?
Only if your contract allows it. Many subcontracts require the principal's written consent and flow down the same obligations to the next tier. You remain responsible to your client for the work, and you still share WHS duties for that site, so check the other company's qualifications, insurance and systems before sending them.